HCRCD is seeking proposals from qualified and experienced contractors to provide all labor, materials, and equipment necessary to carry out the Post Fire Six Rivers 2022 Restoration Project Phase 3 . Proposals for the Project will be received by the HCRCD until 5 p.m. on August 28, 2026. This project is to be conducted on private lands located near Willow Creek, CA. There is a non-mandatory pre-proposal meeting on Monday, August 24 at 11:00am.
HCRCD received the following proposals:
| Contractor | Score | Cost/acre (mech.) | Cost/acre (man.) | Average cost/acre | Loading/hour | Transportation/hour | Total Cost |
| Karl Benemann Benemann | 70% | $12,500.00 | $10,500.00 | $11,500.00 | $315.00 | $320.00 | $373,500.00 |
| Coleman Environmental Engineering | 89% | $7,900.00 | $4,000.00 | $5,950.00 | $- | $160.00 | $217,600.00 |
| Mattole Restoration Council * | 96% | $6,700.00 | $5,800.00 | $6,250.00 | $275.00 | $200.00 | $201,400.00 |
| Washburn Enterprises | 73% | $11,191.66 | $1,670.00 | $6,430.83 | $530.00 | $370.00 | $280,290.00 |